Construction Management Engineering

Activity Based Costing (ABC)

ABC costing

What is Activity Based Costing?

Activity Based Costing (ABC) is a method for developing estimation for cost in which the construction project is subdivided into discrete, quantifiable activities. The activity should be definable where productivity can be controlled in units. After the construction project is decomposed into its activities, a cost estimate is
prepared for all projects’ activities. These single cost estimates will contain all materials, labors, equipment, and subcontracting costs, including overhead, for each activity. Each complete single estimate is added to the others to obtain a total estimate. Contingency, Escalation can be calculated for each activity or after all the activities have been summed. ABC is a very powerful tool, but it isn’t appropriate for all cost estimates.

Activity Based Costing Methodology

Construction firms have collected cost data from a multitude of different construction projects. The amount of work associated with this cost was also collected with the cost data. For example, collected data included the cost of the material, labor, equipment, and overhead to paint a room, the amount of surface area painted, and the labors required to paint the room. This best practice allowed construction professionals to obtain a cost per area and labor resources per area.

ABC equation:

C/A = HD + M + E + S

where C/A = Estimated cost per activity
H = no. of hours of labor required to perform the activity one time
D = Wages per labor hour
M = Costs of material required to perform the activity one time
E = Costs of equipment to perform the activity one time
S = Costs of subcontracting to perform the activity one time

 

The activity total cost will be based on the number of times the activity is performed during a specific time frame. Cost estimators or QS engineers have collected large databases of activity-based cost information.

Use of Activity Based Costing Methodology

ABC methodology is used when a construction project can be divided into defined activities.
These activities are at the lowest function level of a construction project at which costs are monitored and performance is evaluated. Depending on the project organization, the activity may coincide with an element of the work breakdown structure or may combine one or more items of the WBS. However, a clear definition for the activities must be set so there is no overlap between them. After defining the activity, the unit of work is established. All activity costs are estimated using the unit of work.

The estimation of work units can be done by performing detailed estimates, using cost estimating relationships, obtaining outside quotes for equipment, etc. All costs including overhead, markups, profit, and should be included in the activity cost.

 

Identification of Activities

When you start to define a single activity, the cost estimator must balance the need for accuracy with the amount of time available to prepare the estimate. A cost estimator may be able to develop an extremely accurate cost estimate by defining smaller activities; however, the amount of time required to prepare ABC estimates for each activity may not justify the increased accuracy. The total estimated cost of the construction project may be sufficiently accurate if 10 activities are used instead of 15. On the other hand, trustworthy cost info may not be accessible if the activity categories are too general. Since the basis for the cost estimate is the activity, it is very important that the activity be selected correctly

Watch ABC  Video

 

See Also
 S-CURVE EXCEL TEMPLATE

error: Content is protected !!